Requirements for Improvements and Development Proposals
July 17, 2008
1.0 Introduction
This document was prepared to assist developers and consultants in designing and managing projects
that conform with the policies of the Bassett Creek Watershed Management Plan (Plan) (September
2004). The Plan, as adopted by the Bassett Creek Watershed Management Commission
(BCWMC), may be reviewed or obtained from the BCWMC website at http://www.bassettcreekwmo.org/.
This document outlines the requirements designed to achieve the BCWMC’s water quality, rate
control control and other goals. It gives a complete listing of the development requirements, water quality
control standards and design criteria that have been adopted by BCWMC and includes:
- Review Process
- The nature of the review process and procedures
- Required submittals/exhibits
- Variance procedures
- Application form
- Types of projects that require a submittal for review
- Development/redevelopment guidelines
- Policies, standards and requirements
- Floodplain requirements
- A description of approved best management practices (BMPs) that meet the BCWMC’s
Level I standards. BMP descriptions have been organized into the following categories:
(1) infiltration systems, (2) filtration systems, and (3) detention systems.
- Requirements for construction erosion and sediment control plan
- Other requirements
2.0 Review
Process
2.1 Procedure for BCWMC Review
The BCWMC established the following procedures for review of improvements and development
proposals:
- The BCWMC will review the applicant’s submittal only after the project has
received
preliminary review by the municipality indicating general compliance with existing local
watershed management plans prepared pursuant to 103B.235.
- The BCWMC meetings are generally held the third Thursday of each month. In order for a
proposed project to be included on the agenda, plans must be submitted to the BCWMC
engineer by the last Friday of the month, prior to the meeting date. Complex projects may
require additional review time. However, not all projects are presented at the BCWMC
meeting for review and approval. All submittals involving floodplains, Bassett Creek trunk
system, appropriations, variances, and underground wet vaults or other alternative BMPs are
presented at the BCWMC meetings. BCWMC engineer review and approval are generally
provided for submittals that are designed in accordance to the BCWMC policies outlined in
this document.
- Upon receipt of a submittal, the BCWMC engineer will review the submittal and prepare
recommendations to the BCWMC. A memorandum describing each project and the engineer’s
recommendations will be sent to the BCWMC approximately one week before each meeting.
Note: the BCWMC engineer will send a letter with comments directly to the municipality and
to the applicant for projects that do not require review at the BCWMC meeting.
- The BCWMC will review and comment upon the submittal at its regularly scheduled meeting.
The BCWMC will approve, conditionally approve, or reject the submittal. A letter with
comments, including a list of deficiencies or required modifications, will be sent to the
municipality and to the applicant. This step is not necessary for projects approved by the
BCWMC engineer.
- The applicant must provide a revised submittal addressing each deficiency, required
modifications, or comment. A letter of approval will be sent to the municipality and to the
applicant after comments have been satisfactorily addressed.
- Emergency work performed by cities (utility repair, emergency traffic issues, health and
safety issues, etc.) and maintenance projects (seal coating and pavement overlays, sediment
and debris removal from crossings and water quality ponds, etc.) are exempt from BCWMC
review. Cities shall inform the BCWMC regarding emergency work, as soon as practical, in
cases that would have required an application under non-emergency conditions.
2.2
Required Exhibits
The applicant shall submit an application form, project review fee, and two sets of plans and
supporting documentation for BCWMC review. The application form must be signed by City staff.
The required exhibits are listed on the application form and further discussed as follows:
- Completed Application form signed by applicant and City staff
- Project review fee. Submit project review fee in accordance with the fee schedule
- Wetland fee (if applicable): Submit wetland fees for projects resulting in BCWMC review of
wetland issues. BCWMC is the local government unit (LGU) administering the Wetland
Conservation Act for the cities of Medicine Lake, Robbinsdale, and St. Louis Park. Contact
the BCWMC engineer regarding wetland review fee.
- Project plans: Submit two copies of project plans (full size and 11-inch x 17-inch sheets),
including at least:
- A scale drawing of the site showing property lines and delineation of lands under
ownership of the applicant
- Proposed and existing stormwater facilities location, alignment, and elevation
- Existing and proposed site contour elevations related to NGVD, 1929 datum, or other
datum used by municipality
- Construction plans and specifications of all proposed stormwater management facilities
- A runoff water quality management plan and computations, signed by a registered
professional engineer, and meeting the minimum requirements described in these standards.
BMP sizing and average depth calculations for water quality ponds must also be provided. A
runoff water quality management plan shall include the following items:
- Delineation of the subwatersheds tributary runoff from offsite, and proposed and existing
subwatersheds onsite
- Delineation of existing onsite wetlands, marshes, and/or floodplain
areas
- Existing and proposed post-development normal, 5-year ,and 100-year stormwater
elevations for the site
- Stormwater runoff volume and rate analyses for existing and proposed conditions for
5-year and 100-year storm events
- All hydrologic, hydraulic, and other computations necessary to design the proposed
stormwater quality management facilities
- Documentation indicating conformance with an existing municipal local watershed
management plan. If a municipal plan does not exist, documentation indicating that the
municipality has reviewed the project.
- Documentation indicating conformance with an existing municipal local watershed
management plan. If a municipal plan does not exist, documentation indicating that the
municipality has reviewed the project. A final erosion control plan meeting the requirements of these standards.
- A checklist of BMPs provided as part of the application form must be submitted
demonstrating that, to the maximum extent practical, the plan has incorporated the structural
and non-structural BMPs, as described in the referenced documents.
- Other items required to support the proposed project.
2.3 Variance
Procedure
The BCWMC has established the following variance procedures:
- Applications for variances shall be filed with the City where the property is being,
redeveloped, or retrofitted and shall state the exceptional conditions of the property and the
peculiar and practical difficulties claimed as a basis for a variance. The applicant shall state on
the application the reasons for requesting the variance, in accordance with all of the requirements
set forth in section (c) below.
- The City shall refer all applications for variances from the BCWMC
requirements to the BCWMC engineer, and such applications shall be reviewed by the
BCWMC. In reviewing the application,
the BCWMC shall take into consideration the criteria, standards, and goals for maintaining and
improving the quality of the watershed’s water resources. To address the applicant’s hardship or special situation, the BCWMC may grant the variance,
contingent upon conditions that the BCWMC may set forth. Alternatively, the BCWMC may
deny the request and set forth reasons for the denial.
- In granting variances, the BCWMC shall make a finding showing that all of the following
conditions exist:
-
(1) There are special circumstances or conditions affecting the property such that the strict
application of the provisions of these standards and criteria would deprive the applicant of the
reasonable use of its land.
-
(2) The variance is necessary for the preservation and enjoyment of a substantial property right of
the applicant.
-
(3) The granting of the variance will not be detrimental to the public welfare or injurious to the
other property in the territory in which the property is situated.
- (4) In applications relating to a use in the 100-year floodplain set forth in Table 5-3 of the Plan,
the variance shall not allow a lower degree of flood protection than the current flood
protection.
- (5) The granting of the variance will not be contrary to the intent of taking all reasonable and
practical steps to improve water quality within the watershed.
3.0 Types of Projects to be Submitted for Review
All persons, municipalities, or other agencies proposing improvements or developments within the
Bassett Creek watershed shall submit sufficient information to the BCWMC to determine the effect
that their proposal may have on the water resources of the watershed within the following guidelines.
The types of improvements and development proposals that must be submitted to the BCWMC for
review include:
3.1 Floodplains
Any proposal which would consist of a major alteration of existing structures, erection of new
structures, filling, floodway encroachment, activities considered incompatible with
acceptable floodplain uses or be subject to damage by the 100-year flood, and is located below the
100-year floodplain elevation included in the Plan (Table 5-3) must be submitted for BCWMC
review. This section shall apply to structures such as bridges, footbridges, culverts, and pipe
crossings of any nature, including sanitary sewer, water supply and electrical and telephone lines.
Specific floodplain policies are included in Section 5.0.
3.2 Floodplain Storage Sites
Any proposal within the limits of the proposed floodplain storage sites (inundation areas) established
by the BCWMC Plan (Table 5-3, Figure 15) that may be in conflict with the minimum requirements
as outlined in the Plan shall be submitted for BCWMC review.
3.3 Lakes, Streams, and Wetlands
Proposals that may affect the water surface elevation, outlet storage capability, shoreline or
streambank, or be incompatible with existing or proposed land use around the lakes, streams, and
wetlands in the Bassett Creek watershed shall be submitted for BCWMC review. The BCWMC will
defer wetland issues in cases where the municipality acts as the local government unit (LGU) for
administering the Wetland Conservation Act, unless its involvement is requested by the municipality.
3.4 Water Resources
Proposals that would alter water resources in the watershed, involve the discharge of industrial or
other waste to any watercourse or storm sewer, require extensive land alteration, are directly tributary
to the watercourses of the watershed, or may otherwise affect the existing water quality shall be
submitted for BCWMC review. In addition, the BCWMC shall be informed of the proposed
application of chemicals or other treatments to lakes and ponds in the watershed.
3.5 Diversion of Surface Water Runoff
Proposals to provide intra- or inter-watershed diversion which may affect flood levels, lake levels,
and minimum streamflows in the watershed shall be submitted for BCWMC review.
3.6 Land Use Changes
Proposed changes in land use, zoning, and local watershed management plans which may require
modification of the BCWMC Plan shall be submitted for BCWMC review.
3.7 Appropriations
Ground or surface water appropriations which may temporarily or permanently alter the existing
ground and surface water levels in the watershed shall be submitted for BCWMC review.
3.8 Utility Crossings
The construction of utilities through or paralleling the defined trunk creek system which require
disturbance of the bed or banks of the creek or the diversion of the creek shall be submitted for
BCWMC review.
3.9 Department of Natural Resources (DNR) Permit Applications
Permit applications to the DNR for work in public waters, including supporting documentation, shall
be submitted for BCWMC review.
3.10 Development/Redevelopment
Proposals that will result in more than 200 cubic yards of cut or fill or more than 10,000 square feet
of grading shall be submitted for BCWMC review. Requirements for erosion control plans are
included in Section 7.0. Projects requiring water quality treatment are described in Section 4.0.
3.11 Road Construction
Road construction or reconstruction proposals which result in more than 1.0 acre of grading shall be
submitted for BCWMC review. Proposals for review include projects resulting in complete removal
of the road surface, exposing the base, and/or removal of the vegetated surface within the road
right-of-way. Examples include road widening projects, ditch work, road replacement, and utility
installation. Road overlay projects and road resurfacing projects which do not disturb the road base
will not be covered by the requirements of this policy. Requirements for erosion control plans are
included in Section 7.0. Note: road construction or reconstruction projects resulting in more than 5.0
acres of grading require review at a BCWMC meeting. The BCWMC engineer will review and
provide comments directly to the municipality for road projects between 1.0 and 5.0 acres.
4.0 General Guidelines for Developments/Redevelopment
Following is a description of project “triggers” for development/redevelopment proposals that describe the level of BCWMC involvement and required treatment. The table in Appendix C summarizes the treatment requirements for development/redevelopment projects.
4.1 Projects Not Requiring BCWMC Review
New projects which result in less than 200 cubic yards of cut and fill or less than 10,000 square feet of grading do not require BCWMC review. Note other review triggers in Section 3.0.
4.2 Projects Requiring Construction Erosion and Sediment Control Plan
When construction is proposed that will result in more than 200 cubic yards of cut or fill or more than 10,000 square feet of grading, an application, fee, and grading, drainage, and erosion control plan must be submitted for BCWMC review. Requirements for construction erosion and sediment control plans are included in Section 7.0.
4.3 Projects Requiring Treatment to Level I Standards
The BCWMC Plan (Section 4.2.2.4, Policy A) requires treatment of all BCWMC-regulated stormwater from new development to Level I Standards. The BCWMC’s rationale for this policy is that obtaining the maximum amount of stormwater treatment at the time of development will help ensure that water quality objectives are achieved throughout the watershed and avoid costly retrofit projects in the future. A project must be designed in accordance with Level I standards of the water quality policy, when the proposed site meets one of the following development or redevelopment criteria:
- A commercial, industrial, institutional, or public development involving a parcel of more than 0.5 acres of land where there is no existing commercial, industrial, institutional, or public development. A
commercial, industrial, institutional or public expansion/addition involving a site that was partially developed prior to adoption of the BCWMC’s Water Quality Policy (September 14, 1994) and involves grading more than 0.5 acres of land. A
commercial, industrial, institutional, or public redevelopment involving a site of more than 5 acres of land where the commercial, industrial, institutional, residential, or public development currently exists (see also Section 4.4).
- A residential development involving a parcel of more than 2 acres and which contains four or more proposed living units. A
residential redevelopment involving more than 10 acres where there are four or more existing living units.
- A road construction or reconstruction project involving a site of more than 1.0 acre of land for which the site runoff is not currently directed to an onsite or regional treatment facility (see also Section 4.6).
- If the BCWMC has approved a local watershed management plan pursuant to 103B.235, or a subwatershed plan within a municipality; the requirements of this policy which are met by the local watershed management plan shall be deemed satisfied upon showing compliance with the local plan.
Section 6.0 of this document outlines design criteria consistent with Level 1 standards for various water quality enhancement features.
4.4 Nondegradation
Policy for Redevelopment Projects
All redevelopment projects that result in an increase in impervious area (except as noted below) must
meet the requirements of Policy A, Section 4.2.2.4 of the BCWMC Plan, which requires
implementation of BMPs to prevent an increase in phosphorus loading from the site. As an
alternative, the entire parcel shall be developed/redeveloped in accordance to Level 1 Standards.
The following are exemptions from the nondegradation policy (Policy A 4.2.2.4) for redevelopment
projects:
- Single family homes (not part of an overall residential
development/ redevelopment involving a site of more than two acres and which contains four or more proposed
living units)
- Project sites (parcel) less than 0.5 acres
- Sites described within the following table:
| Parcel
size (acres) |
Exemption
applies if added impervious surface area is no more than: |
| 0.5 -
1.0 |
1,000
square feet |
| 1.0 - 5.0 |
2,000
square feet |
| Over 5.0 |
10,000
square feet |
4.5 Site Expansion/Addition Projects
For commercial, industrial, institutional, or public expansion/addition projects, the BCWMC realizes
that existing development may limit the type of BMPs that can be implemented for the entire site. The
most desirable BMP reduces pollutants to the maximum extent practicable and reduces runoff. At a
minimum, a wet detention basin or other approved BMP must be constructed to serve the
expansion/addition and, if applicable, the increase in tributary drainage area of the basin. Other
appropriate BMPs will be required for the existing development if wet detention for the increased
tributary drainage area is not practical. The BCWMC will work with the project applicant to assist
with determining the appropriate temporary and permanent BMPs to implement for the project.
4.6 Road Projects
BMPs must be considered to improve the quality of stormwater runoff from road construction and
reconstruction projects. The most desirable BMP reduces pollutants to the maximum extent
practicable and reduces runoff. The BCWMC realizes that existing development and right-of-way
constraints will limit the type of BMPs that can be implemented. At a minimum, temporary measures
will be required to address erosion and sediment control during construction. The BCWMC will work
with the project applicant to assist with determining the appropriate temporary and permanent BMPs
to implement for the project. The project applicant must submit a description of the evaluation
process used to identify feasible BMPs to be implemented on the project.
5.0 Floodplain Policies
The BCWMC adopted the following policies regarding floodplain regulation within the Bassett Creek
watershed (see policies in Section 5.2.2.2 of the Plan):
- The floodplain of Bassett Creek is defined as that area lying below the 100-year flood
elevations as shown in Table 5-3 of the Plan, or as subsequently revised due to channel improvement, storage site development, or requirements established by appropriate state or federal governmental agencies. (Policy F)
- Land use types that would be damaged by flood waters or that would result in increased flooding are not permitted within the floodplain. (Policy G)
- Allowable types of land use that are consistent with the floodplain include: recreation areas, parking lots, excavations and storage areas, public utility lines, agriculture, and other open space uses. Permanent storage piles, fences, and other obstructions which would collect debris
or restrict flood flows are not allowed. (Policy G)
- Filling will generally not be allowed within the floodplain. Proposals to fill within the
established floodplain must obtain BCWMC approval and must provide compensating storage and/or channel improvement so that the flood level shall not be increased at any point along
the trunk system due to the fill. (Policy H)
- Expansion of existing non-conforming land uses within the floodplain will be prohibited unless they are fully flood-proofed in accordance with existing codes and regulations. (Policy I)
- The lowest floor of all permanent structures must be at least 2 feet above the established 100-year floodplain elevation. (Policy J)
- Project applicants must apply BMPs to reduce the volume of stormwater runoff, to the maximum practical extent. Examples of stormwater runoff volume reduction methods include: (Policy D)
- Reducing the amount of planned impervious surface (as areas develop)
- Reducing the amount of impervious surface (during redevelopment)
- Promoting infiltration
- Economic considerations alone will not be a sufficient reason to alter the floodplain.
(Policy L)
- The BCWMC will not approve any diversions of surface water within, into, or out of the
watershed that may have a substantial adverse effect on stream flow or water levels at any
point within the watershed. Plans for intra- or inter-watershed diversions must include an
analysis of the effects of the diversion on flooding, water quality, and aesthetic quality along
the creek. The BCWMC will review diversion plans to determine the effect of the proposal on
the Bassett Creek watershed and such plans will be subject to BCWMC approval. If it is
necessary to divert surface water runoff to another watershed, every effort must be made to
ensure that there is no fish migration from one watershed to another. (Policy O)
6.0 Level I
Standards
The Plan (see Section 4.2.2.4, Policy A) requires that development proposals must be designed to
meet the BCWMC’s Level I water quality standard (Level I standards). Design criteria for several BMPs that meet the BCWMC’s Level I standards have been adopted by the BCWMC. Except as
noted, the BCWMC-approved BMPs include:
Infiltration Systems
- Infiltration Basin: An infiltration basin is a stormwater runoff impoundment designed to
capture and hold stormwater runoff and infiltrate it into the ground over a period of days. It
does not retain a permanent pool of water. Generally, infiltration basins are suitable for sites
with gentle slopes, permeable soils, relatively deep groundwater levels, and a small tributary
watershed area (less than two acres, ideally).
Filtration Systems
- Surface Sand Filter: A surface sand filter consists of a pretreatment basin, a water storage
reservoir, flow spreader, and under-drain piping. A basin liner may also be needed if the
treated runoff cannot be allowed to infiltrate into the soil underlying the filtration basin
because of groundwater concerns. Sand filters are adaptable, and have few site constraints.
They can be applied in areas with thin soils, high evaporation rates, low soil-infiltration rates,
and limited space.
- Bioretention Basin: A bioretention basin is a shallow, landscaped depression that receives
stormwater runoff. Stormwater flows into the bioretention basin, ponds on the surface, and
gradually filtrates into the soil bed. Filtered runoff is collected by an under-drain system and
discharged to the storm sewer system or directly to receiving waters. Bioretention basins
should usually be used on sites with tributary areas less than two acres. Bioretention basins
can be applied in almost any soils, since runoff percolates through an engineered soil bed.
Detention Systems
- Water Quality Pond: A water quality pond (also known as wet pond, detention basin, water
quality basin, or “NURP” pond [if the pond incorporates specific design parameters]), is a
constructed stormwater pond that retains a permanent pool of water. Water quality ponds are
appropriate for sites where there are no space restrictions.
- Underground Wet Vault: A wet vault is an underground structure designed to provide
temporary and permanent storage for stormwater runoff from a specified storm event. Wet
vaults have a permanent pool of water which dissipates energy and improves the settling of
particulate stormwater pollutants. Wet vaults are typically used for commercial, industrial, or
roadway projects if there are space limitations precluding the use of other treatment
BMPs. All proposed wet vaults must also be reviewed and approved by the BCWMC at its monthly
meeting.
Note: Sections 6.1 – 6.3 present the design and maintenance requirements for the BCMWC approved
BMPs. These design requirements were developed from the following documents:
- Bassett Creek Watershed Management Commission, Watershed Management Plan (Plan) September 2004).
- Minnesota Urban Small Sites BMP Manual
Metropolitan Council, July 2001 (Minnesota BMP Manual) http://www.metrocouncil.org/environment/water/BMP/manual.htm
- State of Minnesota Stormwater Manual, MPCA, November 2005
(Minnesota Stormwater Manual). http://www.pca.state.mn.us/water/stormwater/stormwater-manual.html
- Protecting Water Quality in Urban
Areas, MPCA, March 1, 2000. http://www.pca.state.mn.us/water/pubs/sw-bmpmanual.html
- Plants for Stormwater Design, Species Selection for the Upper Midwest. MPCA, July 2003. http://proteus.pca.state.mn.us/publications/manuals/stormwaterplants.html
6.1 Infiltration Systems
6.1.1 Infiltration Basin Design and Maintenance Requirements
6.1.1.1 Description
An infiltration basin is a stormwater runoff impoundment designed to capture and hold stormwater
runoff and infiltrate it into the ground over a period of days. It does not retain a permanent pool of
water. A key feature of an infiltration basin is its vegetation. It is important to vegetate the bottom of
the basin with deep-rooted plants to increase the infiltration capacity of the basin.
For infiltration basins to perform as designed, pretreatment of stormwater must be provided to remove
as many of the suspended solids from the runoff as possible before the water enters the infiltration
basin.
Infiltration basins have limited capabilities for controlling peak discharge from storms greater than
the design storm. Because infiltration basins will not significantly affect peak discharges of runoff,
they must be used in conjunction with other BMPs to meet peak runoff rate control requirements.
6.1.1.2 Site Analysis
Before an infiltration system can be designed, a site sensitivity analysis must be performed. This
evaluation may eliminate an infiltration practice from consideration because of soil characteristics or
potential effects on groundwater. Because of varying geologic settings, a site evaluation needs to be
tailored to the specific site conditions.
The suitability of using infiltration basins on a site depends on numerous site factors, including soils,
slope, depth to water table, depth to bedrock or impermeable layer, tributary watershed area, land use,
proximity to wells, surface waters, foundations, and others. Generally, infiltration basins are suitable
for sites with gentle slopes, permeable soils, relatively deep groundwater levels, and a small tributary
watershed area (less than two acres, ideally).
When performing a site evaluation, the following items must be considered:
- Geology: A site with highly sensitive geology, such as one with a surficial sand aquifer, may
eliminate this practice from consideration.
- Groundwater: The seasonally high water table must be far enough below the bottom of the
infiltration basin to allow the structure to function hydraulically and to allow trapping and
treatment of pollutants by the soil. Specifically, the seasonally high groundwater table is
recommended to be at least 3 feet from the bottom of the infiltration basin. Basins should be
located at least 150 feet away from drinking water sources to limit the possibility of
groundwater contamination, and should be situated at least 10 feet downgradient and 100 feet
upgradient from building foundations to avoid potential seepage problems.
- Soils: Sites with clayey
soils may not be appropriate for infiltration basins. If the
infiltrations rate of the site's soils is not acceptable, the
filtration family of BMP systems should be considered (see Section
6.2).
- Drainage Area: Generally,
the tributary drainage area to any individual infiltration basin
must be restricted to two acres or less.
- Wetlands: Wetland issues
must be assessed to ensure the BMP conforms to the Wetland
Conservation Act and other wetland regulations.
6.1.1.3 General Design
Considerations
6.1.1.3.1 Design Volume
The infiltration basin design volume must be no less than 0.5 inches of runoff from the tributary
impervious surfaces, while the remaining runoff bypasses the infiltration basin.
6.1.1.3.2 Off-line Placement
The purpose of the basin is to temporarily store surface runoff and allow it to infiltrate through the
bottom and sides of the basin. A flow splitter or weir is typically used to divert runoff into an off-line
infiltration basin. Infiltration basins provide total peak discharge, runoff volume, and water quality
control for all storm events equal to or less than the design storm. Storm events greater than the
design storm simply continue down the larger conveyance system, bypassing the infiltration basin.
6.1.1.3.3 Pretreatment
Pretreatment devices such as proprietary environmental stormwater treatment systems, grit chambers,
grass swales with check dams, filter strips, or sediment forebays/traps are a fundamental component
of any BMP system relying on infiltration and must be incorporated into the design. It is
recommended that pretreatment devices be designed to remove at least 25-30% of sediment loads.
- Sediment forebays/traps for pretreatment should be sized to treat a minimum of 25% of the
design volume.
- Grit chambers for pretreatment should be designed and sized to provide theoretical settlement
of a 0.3-mm grit particle in still water at 10°C (based on Stoke’s Law) and provide sufficient
storage volume for the settled particles consistent with the maintenance schedule.
- Grass filter strips, should be at least 20 feet long for new sites and at least 10 feet long for
retrofits.
6.1.1.3.4 Infiltration Rate
Infiltration volumes and facility sizes shall be calculated using the appropriate hydrological soil
group classification and design infiltration rate from Table 1. The design infiltration rate shall be
selected from Table 1 based on the least permeable soil horizon within the first five feet below the
bottom elevation of the proposed infiltration basin. Soil horizon must be classified under direction of
a licensed soil scientist, geologist, or engineer.
Table 1 Design Infiltration
Rates
| Soil
Group |
Rate |
Soil
Textures |
ASTM
Unified Soil Class Symbols |
| A |
1.60 in/hr |
Gravel, sandy gravel, or
silty gravel |
GW, GP, GM, SW |
| 0.80 in/hr |
Sand, loamy sand, or
sandy loam |
SP |
| B |
0.60 in/hr |
Silt loam |
SM |
| 0.30 in/hr |
Loam |
MH |
|
C |
0.20 in/hr |
Sandy clay loam |
ML |
| Source: Minnesota
Stormwater Manual, November 2005. |
|
D |
0.03 in/hr |
Clay loam, silty clay
loam, sandy clay, silty clay, or clay |
GC, SC, CL, OL, CH, OH |
| Source:
Minnesota BMP Manual, July 2001. |
As an alternative, the applicant may complete double-ring infiltrometer test measurements at the
proposed bottom elevation of the infiltration BMP to the requirements of ASTM
D3385. The measured infiltration rate shall be divided by the appropriate correction factor selected from the
Minnesota Stormwater Manual. This test must be completed under the direction of a licensed soil
scientist, geologist, or engineer.
6.1.1.3.5 Duration of Ponding
The drawdown time for infiltration basins shall be 48 hours (or up to 72 hours if justification can be
provided) from the peak water level in the infiltration basin. The depth and area of the infiltration
basin must be adjusted accordingly. Certain types of vegetation will require shorter ponding duration
to survive storm events.
6.1.1.3.6 Maximum Depth
After the infiltration rate of the soil has been determined, the maximum depth of the infiltration basin
is calculated with the following equation:
dmax = ( f ) * ( Tp )
Where: dmax
= maximum design depth (inches),
f = soil infiltration rate (in/hr), and
Tp = design ponding time (hours).
The maximum depth and ponding time of the infiltration area must promote the survival of vegetation. The maximum depth shall be calculated from Table 1 and shall be no greater than 2 feet
unless justification for increased depth can be provided.
6.1.1.3.7 Basin Slopes
The bottom of the basin must be graded as flat as possible (1% or less is recommended) to provide
uniform ponding and infiltration of the runoff across the floor. The side slopes of the basin should be
no steeper than 3H:1V (flatter slopes are preferred) to allow for proper stabilization and maintenance.
6.1.1.3.8 Basin Shape
The length and width of the basin should be determined by the characteristics of the site in question
(topography, size and shape). A desirable length-to-width ratio for an infiltration basin is 3:1 or
greater.
6.1.1.3.9 Plants
Plants are an important component of an infiltration basin. Plants remove water through evapotranspiration and remove pollutants and nutrient through uptake. It is important to vegetate the
bottom of the basin with deep-rooted plants to increase the infiltration capacity of the basin. The plant
species selected for a infiltration basin must be designed to survive frequent periods of inundation
during runoff events and drying during inter-event periods.
The bottom and side slopes of the basin must be stabilized within seven days following construction.
Vegetative buffers around the perimeter of the basin are recommended for erosion control and
additional sediment and nutrient removal. A diversity of plant species is
recommended to allow for best survivability. Plants that are tolerant of both wet weather and drought must be used.
Plant recommendations based on different site conditions are included in
Plants for Stormwater Design, Species Selection for the Upper Midwest (MPCA, July 2003).
6.1.1.3.10 Inflow/Bypass
If runoff is delivered by a storm drain pipe or along the main conveyance system, the infiltration
basin should be designed as an off-line system to convey high flows around the basin. This will
necessitate the construction of a flow splitter upstream of the basin.
To prevent incoming flow velocities from reaching erosive levels and scouring the basin floor,
inlet channels to the basin should be designed to terminate in a broad apron, which spreads the runoff more
evenly over the basin surface to promote better infiltration.
6.1.1.3.11 Overflow
All infiltration basins should have an emergency spillway capable of passing runoff from large storms
without damage to the impounding structure.
6.1.1.3.12 Groundwater Mounding
Calculations to determine groundwater mounding may be necessary in cases where slope stability is a
concern and/or a high water table is encountered.
6.1.1.4 Sequencing and Construction
- Prior to construction, the area of infiltration basin must be protected by silt fence,
construction fence, or other method to prevent construction equipment from
compacting the
underlying soils.
- To the extent possible, the infiltration basin must be constructed after the
remaining site and
tributary area has been graded and stabilized.
- To the extent possible, excavation must be performed by equipment with tracks
exerting
relatively light pressures to prevent the basin floor from being compacted,
which reduces the
infiltration capacity.
- After final grading, the basin floor must be tilled to a depth of at least six inches to
provide a
well-aerated, porous surface texture. Six inches of compost must be tilled
in at this time.
- The bottom and side slopes of the basin must be stabilized within seven days
following
construction.
6.1.1.5 Maintenance
Maintenance is required for the proper operation of infiltration basins. The city must ensure that a
maintenance agreement and maintenance plan is prepared for operation of infiltration basins.
Following are maintenance requirements from the Minnesota Stormwater Manual
(MPCA, November 2005) and the Minnesota BMP Manual (Metropolitan Council, July 2001):
- The plan must identify owners, parties responsible for maintenance, and an
inspection and maintenance checklist and schedule.
- Pretreatment devices for basins must be inspected and cleaned at least twice a
year.
- Inspections must occur after every rainfall greater than 0.5-inches in the first year after
construction to ensure proper stabilization and function. Attention must be paid to how long
water remains standing in the basin after a storm; water standing within the basin more than
48 hours after a storm indicates that the infiltration capacity may have been overestimated.
Factors responsible for clogging (such as upland sediment erosion and excessive compaction
of soils) must be repaired immediately. Also, the newly-established vegetation must be
inspected to determine if any remedial actions (reseeding, irrigation, etc.) are necessary.
- Thereafter, the infiltration basin must be inspected at least twice per year.
Important items to check include: differential accumulation of sediment, erosion of the basin floor, condition of
riprap and the health of the vegetation. Eroded or barren spots must be replanted immediately
after inspection to prevent additional erosion and accumulation of sediment.
- Sediment removal within the basin must be performed when the sediment is dry enough so
that it is cracked and readily separates from the basin floor to prevent smearing of the basin
floor.
- The surface of the infiltration basin may become clogged with fine sediment over time. Core
aeration or cultivating of non-vegetated areas may be required to ensure adequate infiltration.
- Light equipment, which will not compact the underlying soil, must be used to remove the top
layer of sediment. The remaining soils must be decompacted by tilling and revegetated as
soon as possible.
- Vegetation must be maintained to control weed growth and maintain the health of the
vegetation in the basin. Weeding once monthly is required during the first two growing
seasons. Weeding two or three times per growing season is required after the first two
growing seasons.
- Adequate access for appropriate equipment and vehicles must be provided for inspection,
maintenance and landscaping upkeep.
- Snow storage is encouraged outside of the infiltration area.
- It is recommended that the maintenance agreement between the city and applicant be filed
against the property with the county.
- Additional general maintenance activities and schedules are provided in the
Minnesota Stormwater Manual, and the Minnesota BMP Manual.
6.2 Filtration Systems
6.2.1 Surface Sand Filter Design and Maintenance Requirements
6.2.1.1 Description
Surface sand filters consist of a pretreatment basin, a water storage reservoir, flow spreader, and
under-drain piping. A basin liner may also be needed if the treated runoff cannot be allowed to
infiltrate into the soil underlying the filtration basin because of groundwater concerns.
The two basic components of a sand filter design are the pretreatment basin and the sand filter. The
pretreatment basin reduces the amount of sediment that reaches the sand filter and helps ensure that
stormwater reaches the sand filter as sheet flow.
Drainage areas directed to each sand filter must be less than five acres in size. Sand filters are
adaptable, and have few site constraints. They can be applied in areas with thin soils, high
evaporation rates, low soil-infiltration rates, and limited space.
Sand filters are most effective when designed as offline BMPs; they are intended primarily for quality
control, not quantity control. A diversion structure, such as a flow splitter or weir, must be provided
to route the “first flush” of runoff into the sand filter, while the remainder continues on to a
stormwater-quantity-control BMP.
6.2.1.2 Design Requirements
6.2.1.2.1 Design Volume
The filtration basin design volume must be no less than 1.0 inches of runoff from the tributary
impervious surfaces, while the remaining runoff bypasses the filtration basin.
6.2.1.2.2 Pretreatment
Pretreatment devices such as proprietary environmental stormwater treatment systems, grit chambers,
grass swales with check dams, filter strips, or sediment forebays/traps are a fundamental component
of any BMP system relying on infiltration and must be incorporated in the design. It is recommended
that pretreatment devices be designed to remove at least 25-30% of sediment loads.
-
Sediment forebays/traps for pretreatment should be sized to treat a minimum of 25% of the
design volume.
-
Grit chambers for pretreatment should be designed and sized to provide theoretical settlement
of a 0.3-mm grit particle in still water at 10°C (based on Stoke’s Law) and provide sufficient
storage volume for the settled particles consistent with the maintenance schedule.
-
Grass filter strips should be at least 20 feet long for new sites and at least 10 feet long for
retrofits.
6.2.1.2.3 General Principles and Sizing
-
The sand filter design is based on Darcy’s law:
Q = KiA = VA (since V = Ki)
where Q = WQ design flow (cfs)
K = hydraulic conductivity (fps)
A = surface area perpendicular to the direction of flow (sf)
i = hydraulic gradient (ft/ft) for a constant head and constant media
depth, computed as follows:
i = ( h + l ) / l
where h = average depth of water above filter (ft), defined
for this
design as d/2
d = maximum storage depth above filter (ft)
l = thickness of sand media (typically 1.5 ft)
When water is flowing into the ground, V is commonly called the filtration rate. It is
ordinarily measured in a percolation test. The filtration rate V changes with head and media
thickness, although the media thickness is constant in the sand filter design. Table 2 shows
values of V for different water depths d (remember, d = 2h), assuming a media thickness of
1.5 feet and a hydraulic conductivity of 1 inch per hour.
Unlike the filtration rate V, the hydraulic conductivity K does not change with head, nor is it
dependent on the thickness of the media, only on the characteristics of the media and the
fluid. The hydraulic conductivity of 1 inch per hour (2.315 x 10-5 fps) used in this design is
based on bench-scale tests of conditioned rather than clean sand. This design hydraulic
conductivity represents a typical sand-bed condition as silt is captured and held in the filter
bed. The designer must determine the correct hydraulic conductivity based on
the actual sand used for the filter bed.
Table 2 Sand
Filter Design Parameters
| |
Sand
Filter Design Parameters |
| Facility ponding depth d
(ft) |
1 |
2 |
3 |
4 |
5 |
6 |
| Filtration rate V (in/hr) * |
1.33 |
1.67 |
2.00 |
2.33 |
2.67 |
3.0 |
| 1/V (min/in) |
44 |
36 |
30 |
26 |
26 |
20 |
* Note: The filtration rate is not used directly but is provided for information. V equals the
hydraulic conductivity K times the hydraulic gradient i. The hydraulic conductivity used is 1 in/hr. The hydraulic gradient = (h + l) / l, where h = d / 2 and l = the sand depth (1.5 ft). |
Source: King County, Washington Surface Water
Design Manual, 1988 (revised 2005)
For a basic sand filter design, it is recommended that the filter must be sized to completely
empty (drawdown time) the design-storm volume in 24 hours or less (or up to 48 hours if
justification can be provided). Water depth above the filter must be no more than 4 feet (or up
to 6 feet if acceptable to the city). A minimum of 1-foot of freeboard is recommended when
establishing the BMP depth.
6.2.1.2.4 Basic Components
Surface sand filters generally include the following layers, from top to bottom: sand,
geotextile, and an under-drain system.
The seasonally high water table must be far enough below the bottom of the sand filter to
allow the structure to function hydraulically and to allow trapping and treatment of pollutants
by the filter.
Runoff discharging to the sand filter must be pretreated (via a presettling basin, for example)
to remove debris and other gross solids and any oil from high-use sites. (The type of
pretreatment device must depend on the type of pollutants present.) The recommended
length-to-width ratio of the presettling basin is 3:1 and the depth should be 3 to 6 feet.
Inlet structures (such as flow spreaders, weirs, or multiple orifice openings) must be designed
to minimize turbulence to spread the flow uniformly across the surface of the filter media.
Stone riprap or other dissipation devices must also be installed to prevent
gouging of the sand
media and promote uniform flow. Offline outlet structures are typically sized for the
15-minute peak flow of a 2-year, 24-hour storm.
An impermeable liner (clay, geomembrane, or concrete) is required under the filter to protect
groundwater where soil contamination is present.
6.2.1.2.5 Sand Specification
The sand in a filter must consist of a medium sand meeting the size gradation (by weight) given in
Table 3. The designer must obtain a grain-size analysis from the supplier to certify that the No. 100
and No. 200 sieve requirements are met. A laboratory analysis to determine the sand’s hydraulic
conductivity K is also highly recommended. The designer must then adjust this number to account for
conditioning of the sand during operation.
Table 3 Medium Sand Specification
| U.S.
Sieve Number |
Percent
Passing |
| 4 |
95 - 100 |
| 8 |
70 - 100 |
| 16 |
40 - 90 |
| 30 |
25 - 75 |
| 50 |
2 - 25 |
| 100 |
<4 |
| 200 |
<2 |
6.2.1.2.6 Under-Drain Systems
Several types of under-drains may be used: a central collector pipe (with lateral feeder pipes or a
geotextile drain strip in an 8-inch gravel backfill or drain rock bed) or a
longitudinal pipe in an 8-inch gravel backfill or drain rock with a collector pipe at the
outlet end.
-
Hydraulically, the system is typically sized for the 15-minute peak flow from a 2-year, 24-hour storm, with 1 foot of head above the invert of the upstream end of the collector pipe.
Local sizing requirements must be used when available.
-
Under-drain pipes are recommended to have internal diameters with a minimum of 6 inches
and two rows of half-inch holes spaced 6 inches apart longitudinally (max.), with
the rows 120 degrees apart (laid with holes downward). The recommended maximum perpendicular
distance between two feeder pipes is 10 feet.
-
The recommended minimum grade of the under-drain piping is 1.0 percent and the
recommended minimum grade of the main collector pipe is 0.5 percent.
-
A geotextile fabric should be used between the sand layer and drain rock or
gravel and placed so that one inch of drain rock or gravel is above the fabric.
Drain rock is recommended to be 1.5- to 0.75-inch rock or gravel backfill,
washed free of clay and organic material.
-
Cleanout wyes with caps or junction boxes are recommended to be provided at
both ends of the collector pipes. Cleanouts must extend to the surface of the filter. A valve box should be
provided for access to the cleanouts.
6.2.1.2.7 Impermeable Liners
Impermeable liners (clay, concrete, geomembrane, etc.) are required when nonconventional soluble
pollutants such as metals and organics are present and where the underflow could cause problems
with structures or groundwater.
6.2.1.2.8 Slopes and
Siting
-
An access ramp with a slope not to exceed 7:1 (horizontal:vertical) or equivalent is
recommended for maintenance purposes at the inlet and the outlet of a surface filter.
-
Side slopes for earthen or grass embankments are recommended not to exceed
3:1 (horizontal:vertical) to facilitate mowing/maintenance.
-
Some cities may require perimeter fencing or benching to reduce safety
hazards.
-
High groundwater may damage underground structures or affect the performance of filter
under-drain systems. Sufficient clearance (at least 3 feet is recommended) between the
seasonal high groundwater level and the bottom of the BMP is necessary to obtain adequate
drainage.
-
Maximum longevity of the sand filter may be achievable by limiting its use only to runoff
from impervious areas to minimize clogging by organic material from turfed surfaces.
6.2.1.3 Sequencing and Construction
- The sand filter is recommended to be constructed after the remaining site and tributary area
has been graded and stabilized.
- To the extent possible, excavation must be performed by equipment with tracks exerting
relatively light pressures to prevent basin floor from being compacted, which reduces the
filtration capacity.
- Sand must be placed uniformly to prevent formation of voids that could lead to
shortcircuiting
(particularly around penetrations for under-drain cleanouts) and to prevent damage
to the underlying under-drain system. To the extent possible, voids between the trench walls
and the geotextile fabric must be avoided.
- Mechanical compaction of the sand filter should be avoided. The sand bed can be
stabilized
by wetting the sand periodically, allowing it to consolidate, and then adding
extra sand. This
process can be repeated until consolidation is complete.
- The bottom and side slopes of the sand filter must be stabilized within seven days following
construction.
6.2.1.4 Maintenance
Maintenance is required for the proper operation of sand filters. The city must ensure that a
maintenance agreement and maintenance plan is prepared for operation of sand filters. Following
are maintenance requirements from the Minnesota Stormwater Manual (MPCA, November 2005)
and the Minnesota BMP Manual (Metropolitan Council, July 2001):
- The plan must identify owners, parties responsible for maintenance, and an
inspection and maintenance checklist and schedule.
- Adequate access to the sand filter must be provided for inspection and
maintenance.
- Sand filters must be inspected after every rainfall greater than 0.5-inches in the first year after
construction; thereafter, the sand filter must be inspected at least twice per year. Maintenance
for sand filters consists of removing the first two or three inches of discolored sand and
replacing it with new sand.
- Silt and sediment is recommended to be removed from the surface of the filter
when an accumulation of one inch has occurred or when the drawdown time
increases beyond 20 percent of design value.
- Sediment removal within the sand filter must be performed when the sediment is dry enough
so that it is cracked and readily separates from the surface to prevent smearing of the filter.
- Vegetation must be maintained as needed. Devices with healthy vegetation tend not to clog.
The use of flood- and drought-resistant varieties will minimize maintenance needs.
- To insure proper performance, sediment, trash, and debris must be removed from
the sand filter and pretreatment basin on a regular basis.
- Snow storage is encouraged outside of the sand filter.
- It is recommended that the maintenance agreement between the city and applicant be filed
against the property with the county.
- Additional general maintenance activities and schedules are provided in the
Minnesota Stormwater Manual, and the Minnesota BMP Manual.
6.2.2 Bioretention System Design and Maintenance Requirements
6.2.2.1 Description
In general, bioretention systems can be described as shallow, landscaped depressions commonly
located in parking lot islands or within small pockets in residential areas that receive stormwater
runoff. Stormwater flows into the bioretention basin, ponds on the surface, and gradually infiltrates
into the soil bed. Pollutants are removed by a number of processes including adsorption filtration,
volatilization, ion exchange and decomposition (Design Manual for Bioretention in Stormwater
Management, Prince George’s County, MD, 1993). Filtered runoff is collected by an under-drain
system and discharged to the storm sewer system or directly to receiving waters. Runoff from larger
storms is generally diverted past the area to the storm drain system.
6.2.2.2 Site Analysis
Before a bioretention basin can be designed, site conditions must be considered to
ensure that a bioretention basin is the appropriate BMP for the site.
- Drainage area: Bioretention basins should usually be used on sites with tributary areas less
than two acres. When used to treat larger areas, they tend to clog. In addition, it is difficult to
convey flow from a large area to a bioretention basin. For larger sites, multiple basins should
be used to treat runoff.
- Available area for the bioretention basin: It is recommended the surface area of the
bioretention basin should be between 5% and 10% of the impervious area
draining to it, with a minimum of 200 square feet for small sites.
- Soils: Bioretention basins can be applied in almost any soils, since runoff
percolates through an engineered soil bed and is returned to the stormwater
system.
- Groundwater: The seasonally high water table must be far enough below the
bottom of the bioretention basin to allow the structure to function hydraulically and to allow trapping and
treatment of pollutants by the soil. Specifically, the seasonally high groundwater table is
recommended to be a least 3 feet from the bottom of the bioretention basin.
- Under-Drain: An under-drain is a perforated pipe in a gravel bed, installed along the bottom
of a soil bed that collects and removes filtered runoff, directing it to a storm drain system.
- Wetlands: Wetland issue must be assessed to ensure the BMP conforms to the Wetland
Conservation Act and other wetland regulations.
6.2.2.3 General Design Considerations
6.2.2.3.1 Design Volume
The bioretention basin design volume must be no less than 1.0 inch of runoff from the tributary
impervious surfaces, while the remaining runoff bypasses the bioretention basin.
6.2.2.3.2 Pretreatment
Pretreatment devices such as proprietary environmental stormwater treatment systems, grit chambers,
grass swales with check dams, filter strips, or sediment forebays/traps are a fundamental component
of any BMP system relying on infiltration and must be incorporated in the design. It is recommended
pretreatment devices be designed to remove at least 25-30% of sediment loads.
Sediment forebays/traps for pretreatment should be sized to treat a minimum of 25% of the
design volume.
Grit chambers for pretreatment should be designed and sized to provide theoretical
settlement of a 0.3-mm grit particle in still water at 10°C (based on Stoke’s Law) and
provide sufficient storage volume for the settled particles consistent with the maintenance schedule.
Grass filter strips should be at least 20 feet long for new sites and at least 10 feet long for
retrofits.
6.2.2.3.3 Maximum Depth
The maximum depth and ponding time of the bioretention basin must promote the survival of
vegetation. Where feasible the bioretention basin must be designed to pond 6 to 9 inches (the
maximum pooling depth may be up to 2 feet if justification for increased depth can be provided).
6.2.2.3.4 Duration of Ponding
Where feasible, the drawdown time for bioretention basins shall be 48 hours (or up to 72 hours if
justification can be provided) from the peak water level in the bioretention basin. The depth and area
of the bioretention basin must be adjusted accordingly. Certain types of vegetation will require
shorter ponding duration to survive storm events.
6.2.2.3.5 Basin Slopes
The bottom of the basin must be graded as flat as possible (1% or less is recommended) to provide
uniform ponding and filtration of the runoff across the floor. The side slopes of the area should be no
steeper than 3H:1V (flatter slopes are preferred) to allow for proper stabilization and maintenance.
6.2.2.3.6 Planting Soil Bed
The planting soil bed provides water and nutrients to support plant life in the bioretention basin.
Stormwater filters through the planting soil bed where pollutants are removed by the mechanisms of
filtration, plant uptake, adsorption, and biological degradation.
-
A well-blended, homogenous mixture of 50-60% sand, 20-30% top soil, and
20-30% organic leaf compost is recommended to provide a soil medium with a high infiltration/filtration
capacity.
-
Sand—Provide clean sand, free of deleterious materials. AASHTO M-6, ASTM C-33 or
MnDOT 3126F with grain size of 0.02-0.04 inches, to the extent possible.
-
Top
Soil—Sandy loam, loamy sand, or loam texture per USDA textural triangle with less
than 5% clay content.
-
Organic Leaf
Compost—MnDOT Grade 2 Compost (provided by vendor approved by
MnDOT’s Turf Establishment and Erosion Prevention Unit).
-
The recommended minimum depth of the prepared soil is 30 inches. However, if large trees
are preferred in the design, a soil depth of 48 -52 inches is recommended to accommodate the
root depth of the proposed trees.
6.2.2.3.7 Plants
Plants are an important component of a bioretention system. Plants remove water
through evapotranspiration and remove pollutants and nutrient through uptake. Plant
roots enhance the infiltration capacity of the soil, providing conduits for percolation. The
plant species selected for a bioretention basin must be designed to survive frequent
periods of inundation during runoff events and drying during inter-event periods.
The bottom and side slopes of the basin must be stabilized with appropriate plants
within seven days following construction. Vegetative buffers around the perimeter of the
basin are recommended for erosion control and additional sediment and nutrient
removal. A diversity of plant species is recommended to allow for best survivability.
Plants that are tolerant of both wet weather and drought must be used.
Plant recommendations based on different site conditions are included in
Plants for Stormwater Design, Species Selection for the Upper Midwest (MPCA, July 2003).
6.2.2.3.8 Inflow/Bypass
-
If runoff is delivered by a storm drain pipe or along the main conveyance system,
the bioretention basin should be designed as an off-line system to convey high
flows around the basin. This will necessitate the construction of a flow splitter
upstream of the basin.
-
To prevent incoming flow velocities from reaching erosive levels and scouring the basin
floor, inlet channels to the basin must be designed to terminate in a broad
apron, which spreads the runoff more evenly over the basin surface to promote better filtration.
6.2.2.3.9 Overflow
All bioretention basins should have an emergency spillway capable of passing runoff
from large storms without damage to the impounding structure.
6.2.2.4 Sequencing and Construction
- Prior to construction, the area of the bioretention basin must be protected by silt
fence,
construction fence or other method to prevent construction equipment from compacting the
underlying soils.
- To the extent possible, the bioretention basin must be constructed after the
remaining site and
tributary area has been graded and stabilized.
- To the extent possible, excavation must be performed by equipment with tracks
exerting
relatively light pressures to prevent the basin floor from being compacted,
which reduces the
infiltration capacity.
- After final grading, the bioretention basin floor must be tilled to a depth of at least 6
inches to
provide a well-aerated, porous surface texture. Six inches of compost must be tilled in at this
time.
- The bottom and side slopes of the basin must be stabilized with appropriate plants
within seven days following construction.
6.2.2.5 Maintenance
Maintenance is required for the proper operation of bioretention basins. The city must
ensure that
a maintenance agreement and maintenance plan is prepared for operation of bioretention basins.
Following are maintenance requirements from the Minnesota Stormwater Manual
(MPCA,
November 2005) and the Minnesota BMP Manual (Metropolitan Council, July 2001):
- The plan must identify owners, parties responsible for maintenance, and an
inspection and
maintenance checklist and schedule.
- Pretreatment devices for bioretention basins must be inspected and cleaned at
least twice a
year.
- Inspections must occur after every rainfall greater than 0.5-inches in the first year
after
construction to ensure proper stabilization and function. Attention must be
paid to how long
water remains standing in the basin after a storm; water standing within the basin more than
48 hours after a storm indicates that the filtration capacity may have been overestimated.
Factors responsible for clogging (such as upland sediment erosion and excessive compaction
of soils) must be repaired immediately. Also, the newly-established vegetation must be
inspected to determine if any remedial actions (reseeding, irrigation, etc.) are necessary.
- Thereafter, the bioretention basins must be inspected at least twice per year.
Important items to check include: differential accumulation of sediment, erosion of
the floor, condition of riprap and the health of the vegetation. Eroded or barren spots
must be replanted immediately after inspection to prevent additional erosion and
accumulation of sediment.
- The surface of the ponding area may become clogged with fine sediment over time.
Core aeration or cultivating of non-vegetated areas may be required to ensure
adequate filtration.
- Sediment removal within the bioretention basin must be performed when the
sediment is dry enough so that it is cracked and readily separates from the floor to
prevent smearing of the floor.
- Light equipment, which will not compact the underlying soil, must be used to
remove the top layer of sediment. The remaining soils must be tilled and
revegetated as soon as possible.
- Vegetation must be maintained to control weed growth and maintain the health of
the vegetation in the basin. Weeding once monthly is recommended during the first
two growing seasons. Weeding two or three times per growing season is recommended after the first two
growing seasons.
- Adequate access for appropriate equipment and vehicles must be provided for
inspection, maintenance, and landscaping upkeep.
- Snow storage is encouraged outside of the bioretention basin.
- It is recommended that the maintenance agreement between the city and applicant
be filed against the property with the county.
- Additional general maintenance activities and schedules are in the
Minnesota Stormwater Manual and the Minnesota BMP Manual.
6.3 Detention Systems
6.3.1 Water Quality Pond Design and Maintenance Requirements
6.3.1.1 Description
Water quality ponds (also known as wet ponds, detention basins, water quality basins, or
“NURP” ponds [if the pond incorporates specific design parameters]), are constructed
stormwater ponds that retain a permanent pool of water. Water quality ponds are generally
on-line, end-of-pipe BMPs. The primary pollutant removal mechanism in a water quality
pond is sedimentation. Significant loads of suspended pollutants, such as metals,
nutrients, sediments, and organics, can be removed by sedimentation. Water quality
ponds have a moderate to high capacity for removing most urban pollutants, depending on
how large the volume of the permanent pool is in relation to the runoff from
the surrounding watershed. Removal efficiency is primarily dependent on the length of time that
runoff remains in the pond, which is known as the pond’s hydraulic residence time
(HRT).
Water quality ponds can also be constructed using multiple cells to enhance removal
efficiency, incorporate skimming and provide accessible maintenance.
6.3.1.2 Site Analysis
- Treatment Standard: Natural or excavated low areas shall be used for the water
quality ponds. Generally accepted reservoir routing procedures using critical
duration runoff events shall be used for design of these areas and outlets. Based on
the BCWMC Plan, all regulated stormwater must be treated to Level I standards
throughout the watershed.
- Alternatives to Onsite Ponds: Alternative water quality management features
may be used where onsite ponds are not feasible. Alternative features must be
designed to provide water quality benefits that equal or exceed design criteria
outlined in existing BCWMC policies.
- Bedrock: As with other stormwater BMPs, soils depth to bedrock and depth to
water table must be investigated before designing a water quality pond. At sites
where bedrock is close to the surface, high excavation costs may make water
quality ponds infeasible. If the soils on the site are relatively permeable or
well-drained, it will be difficult to maintain a permanent pool. It may be necessary to
line the bottom of the water quality pond to reduce infiltration.
- Wetlands: Wetland issues must be assessed to ensure the BMP conforms to the
Wetland Conservation Act and other wetland regulations.
6.3.1.3 Design Requirements
6.3.1.3.1 Design Volume
-
The permanent pool (dead storage) volume below the principal spillway (normal
outlet) must be greater than or equal to the runoff volume from a 2.5-inch,
24-hour storm over the project site, assuming full development. The project site
includes all tributary area draining to the pond.
-
The dead storage volume must be calculated separately from impervious and
pervious surfaces to prevent artificially low volumes due to composite curve
numbers.
-
The entire tributary drainage area must be considered in computing the dead
storage volume, assuming full development of the drainage area. For design
purposes, the water quality volume must be considered an instant flow to the
pond, not an inflow-outflow calculation. In other words, this volume must be
considered to arrive at the pond all at once, rather than over the course of several
hours or days. The assumption of instant runoff is conservative, but it
accounts for a great deal of the variability that occurs in both storm events and runoff
conditions.
6.3.1.3.2 Average Depth
The permanent pool average depth (basin volume/basin surface area) shall be > 4 feet,
with a maximum depth of < 10 feet. For small ponds (less than 3 acre-feet in volume)
average depth shall be > 3 feet, with a maximum depth of < 10 feet. An “effective
average depth” (“effective volume”/ “effective surface area”) may be calculated for ponds
that include benches. The “effective volume” and “effective surface area” are computed
by extending the basin side slopes below the basin bench vertically to the water
surface.

6.3.1.3.3 Emergency Overflow
An emergency overflow (emergency outlet) must be in place and adequately designed
to accommodate the 100-year frequency critical duration rainfall event.
6.3.1.3.4 Basin Side Slopes
Basin side slopes above the normal water level should be no steeper than 3:1, and
preferably flatter, to allow for proper stabilization and maintenance. A basin bench with
a minimum width of 10 feet and 1-foot deep below the normal water level is
recommended to enhance wildlife habitat, reduce potential safety hazards, and improve
access for long-term maintenance. Slopes that extend below the bench to the bottom of
the pond must be at a stable slope, usually no steeper than 3:1.
6.3.1.3.5 Short-Circuiting
To prevent short-circuiting, the distance between the major inlets and normal outlet
must be maximized.
6.3.1.3.6 Flood Pool (Live Storage)
The flood pool (live storage) volume above the principal spillway shall be such that the
peak discharge rate from the 5-year and 100-year frequency, critical duration storms do
not exceed the peak discharge for similar storms under predevelopment conditions.
6.3.1.3.7 Pond Shape
To maximize stormwater contact and residence time in the pool, a length-to-width ratio
of 3:1 is recommended. A minimum pool surface area of 0.25 acres is recommended.
Performance of the water quality pond may be enhanced by enlarging the surface area to increase volume, as opposed to
deepening the pool. However, average depth criteria must be achieved.
6.3.1.3.8 Multi-Stage Outlets
Water quality ponds may be designed with a multi-stage outlet structure to control
discharges from different size storms. Usually the pond is designed to control multiple
design storms (e.g., 2- and 10-year storms) and safely pass the 100-year storm event.
However, the design storm may vary depending on local conditions and requirements.
6.3.1.3.9 Extended Detention
Extended detention of runoff from the more frequent (1-year to 5-year) storms is
recommended by designing a principal spillway which includes a perforated vertical
riser, small orifice outlet, or a compound weir.
6.3.1.3.10 Stormwater Outfalls
The design must include effective energy dissipation devices that reduce outlet
velocities to 4 fps or less. These outlets shall consist of stilling basins or other such
devices that prevent erosion at all stormwater outfalls into the water quality pond, and at
the basin outlet. Storm sewer outfalls must extend to the water quality pond or other
receiving water body and must discharge at or below its normal water elevation.
6.3.1.3.11 Outlet Structure (Skimming)
Trash and floatable debris skimming devices must be placed on the outlet of all onsite
water quality ponds to provide treatment up to the critical duration 5-year storm event.
Submerged inlets, permanent baffled weirs or similar devices may be employed. Timber
baffled weirs are discouraged. To the extent possible, velocities through the devices
shall be less than 0.5 fps. The top of submerged inlets shall be at least one foot below
the normal water surface.
6.3.1.3.12 Pretreatment
Pretreatment, such as grit chambers, swales with check dams, filter strips, or sediment
forebays/traps should be considered to extend the life of the water quality pond.
6.3.1.3.13 Flow Conveyance Capacity
Onsite water quality ponds shall avoid or minimize increases in predevelopment runoff
rates to the greatest extent practical. The capacity of the receiving body to convey
and/or store the runoff shall also be considered so as to not adversely affect water
levels off the site.
6.3.1.4 Sequencing and Construction
- To the extent possible, water quality ponds must be constructed in the initial
phases of a
development project in order to treat site runoff during construction.
- If the water quality pond is used as a sediment trap during construction, all
sediment
deposited during construction must be removed before normal operation begins.
- During construction of the basin, discharge of waterborne sediments to
downstream water
bodies must be prevented, to the extent possible.
- The side slopes of the water quality pond must be stabilized within seven days
following
construction.
6.3.1.5 Maintenance
Maintenance is required for the proper operation of water quality ponds. The city must
ensure that a maintenance agreement and maintenance plan is prepared for operation of
water quality ponds. Following are maintenance requirements from the Minnesota
Stormwater Manual (MPCA, November 2005) and the Minnesota BMP Manual
(Metropolitan Council, July 2001):
- The plan must identify owners, parties responsible for maintenance, and an
inspection and maintenance checklist and schedule.
- Water quality ponds must be inspected after every rainfall greater than 0.5-inches
in the first year after construction.
- Thereafter, water quality ponds must be inspected at least twice per year during
the growing season to ensure that they are operating as designed. Potential
problems that must be checked include: subsidence, erosion, cracking or tree
growth on the embankment, damage to the emergency spillway; sediment accumulation around the outlet; and erosion within the basin
and banks. Any necessary repairs must be made immediately. During inspections, changes to
the water quality pond or the tributary watershed must be noted, as these may affect
basin performance.
- Accumulated trash and debris must be removed from the side slopes,
embankment, emergency spillway, weirs, and trash grates as often as needed (at
least twice during the growing season). Accumulated sediment in the forebay must
be inspected at the same time.
- Sediment must be removed from the pond, as necessary. The frequency of
sediment removal depends on the years of sediment accumulation that were
incorporated into the design volume of the water quality pond’s permanent pool and
forebay and on the occurrence of any highloading events.
- Sediment removal from water quality ponds and disposal is currently regulated by
the MPCA. Sediment testing, disposal and permitting may be required and shall be
investigated on an individual site basis. Sediments must be tested for toxicants in
compliance with current disposal requirements as required by local, state, or
federal laws or regulations.
- Adequate access for appropriate equipment and vehicles must be provided for
inspection, maintenance and landscaping upkeep.
- It is recommended that the maintenance agreement between the city and applicant
be filed against the property with the county.
- Additional general maintenance activities and schedules are in the
Minnesota Stormwater Manual and the Minnesota BMP Manual.
6.3.2 Underground Wet Vault Design and Maintenance Requirements
6.3.2.1 Description
An underground wet vault is an underground structure designed to provide temporary and
permanent storage for stormwater runoff from a specified storm event. Wet vaults have a
permanent pool of water which dissipates energy and improves the settling of particulate
stormwater pollutants. Wet vaults are typically on-line, end-of-pipe BMPs.
Pollutant removal mechanisms for particulate pollutants in wet vaults are similar to water
quality ponds. The primary pollutant removal mechanism in a wet vault is sedimentation.
Significant loads of suspended pollutants, such as metals, nutrients, sediments, and
organics, can be removed by sedimentation. However, in a wet vault, the permanent pool
of water is covered by a lid which blocks sunlight from entering the facility, limiting
light-dependent biological activity. Consequently, biological pollutant removal mechanisms
that function in the surface water quality ponds are not a part of stormwater treatment in a
wet vault.
Wet vaults are typically used for commercial, industrial, or roadway projects if there are
space limitations precluding the use of other treatment BMPs.
6.3.2.2 General Design Requirements
6.3.2.2.1 Design Volume
-
The permanent pool (dead storage) volume below the principal spillway (normal
outlet) must
be greater than or equal to the runoff volume from a 2.5-inch, 24-hour storm over the project
site, assuming full development. The project site includes all tributary area draining to the
structure.
-
The “dead storage” volume shall be calculated separately from impervious and
pervious
surfaces to prevent artificially low volumes due to composite curve numbers.
-
The entire tributary drainage area must be considered in computing the dead
storage volume,
assuming full development of the drainage area. For design purposes, the water quality
volume must be considered an instant flow to the wet vault, not an inflow-outflow
calculation. In other words, this volume must be considered to arrive at the wet vault all at
once, rather than over the course of several hours or days. The assumption of instant runoff is
conservative, but it accounts for a great deal of the variability that occurs in both storm events
and runoff conditions.
6.3.2.2.2 Average Depth
The permanent pool average depth (vault volume/vault surface area) shall be > 4 feet, with
a
maximum depth of < 10 feet.
6.3.2.2.3 Vault Inlet Structures and Pipes
-
To the extent possible, the inlet to the wet vault shall be submerged with the inlet
pipe invert a minimum of 3 feet from the vault bottom and the top of the inlet pipe
shall be submerged at least 1 foot. The submerged inlet is intended to dissipate
energy of the incoming flow. The distance from the bottom is intended to minimize
resuspension of settled sediment. Alternative inlet designs that accomplish these
objectives are acceptable.
-
Unless designed as an off-line facility, it is recommended the capacity of the
outlet pipe and available head above the outlet pipe should be designed to convey
flows larger than the water quality design flow for developed site conditions without
overtopping the vault. The available head above the outlet pipe is recommended to
be a minimum of 6 inches.
-
A gravity drain for maintenance is recommended if grade allows. Gravity drains
should be as low as the site situation allows; however, the invert shall be no lower
than the average sediment storage depth to prevent plugging.
-
Wet vaults may be constructed using arch culvert sections provided the top area
at the normal water surface is, at a minimum, equal to that of a vault with vertical
walls designed with an average depth of 6 feet. This is to prevent decreasing the
surface area available for oxygen exchange.
-
Galvanized materials shall be prohibited.
-
Adequate vents in the vault or other provisions must be included to ensure the
water in the vault does not become “stagnant” resulting in anoxic conditions and
the release of phosphorus in the water column. Lockable grates instead of solid
manhole covers are recommended to increase air contact with the wet pool.
-
Operational access to the valve that controls the gravity drain must be provided to
the finished ground surface.
6.3.2.2.4 Short-Circuiting and the Promotion of Plug Flow
To prevent short-circuiting, water must be forced to flow, to the extent practical, to all
potential available flow routes, avoiding “dead zones” (corners, etc.) and maximizing the
time that water stays in the vault during the active part of a storm. Design features that
encourage plug flow and avoid dead zones are:
-
Providing a broad surface for water exchange across cells rather than a
constricted area.
-
Maximizing the distance between the major inlets and normal outlet.
-
The ratio of flowpath length to width from the inlet to the outlet is recommended to
be at least 3:1.
-
To the extent possible, all inlets must enter the first cell. If there are multiple
inlets, the length-to-width ratio should be based on the average flowpath length for
all inlets.
-
Flow rates must be uniform to the extent possible and not increased between
cells.
6.3.2.2.5 Flood Pool (Live Storage)
The flood pool (live storage) volume above the principal spillway shall be such that the
peak discharge rate from the 5-year and 100-year frequency, critical duration storm does
not exceed the peak discharge for a similar storm under predevelopment conditions.
6.3.2.2.6 Outlet Structure (Skimming)
Trash and floatable debris-skimming devices shall be placed on the outlet of all wet vaults
to provide treatment up to the critical-duration 5-year storm event. Submerged inlets,
permanent baffled weirs, or similar devices may be employed. Timber baffled weirs are
discouraged. To the extent possible, velocities through the devices shall be less than 0.5
fps. The top of submerged inlets shall be at least one foot below the normal water
surface.
6.3.2.2.7 Pretreatment
Pretreatment, such as grit chambers, swales with check dams, filter strips, or sediment
forebays/traps should be considered to extend the maintenance frequency of the wet
vault.
6.3.2.2.8 Flow Conveyance Capacity
Onsite wet vaults shall avoid increases in predevelopment runoff rates to the greatest
extent practical. The capacity of the downstream receiving body to convey and/or store
the runoff shall also be considered so as to not adversely affect water levels off the site.
6.3.2.2.9 Vault Structures
Detailed examples of wet vault structures are provided in the following document:
6.3.2.3 Sequencing and Construction
- Wet vaults may be constructed in the early phases of a development project in
order to treat
site runoff during construction.
- Sediment that has accumulated in the wet vault must be removed after the
remaining site and
tributary area has been graded and stabilized.
6.3.2.4 Maintenance
Maintenance is required for the proper operation of wet vaults. The city must ensure that a
maintenance agreement and maintenance plan is prepared for operation of wet vaults.
Following are maintenance requirements from the Minnesota Stormwater Manual
(MPCA, November 2005) and the Minnesota BMP Manual (Metropolitan Council, July 2001):
- The plan must identify owners, parties responsible for maintenance, and an
inspection and maintenance checklist and schedule.
- Following construction, the underground wet vault must be inspected after every
rainfall greater than 0.5-inches in the first year after construction. Thereafter, wet
vaults must be inspected at least annually.
- Structural inspection shall be performed every 5-years by a registered professional
engineer.
- Accumulated trash, floating debris and petroleum products must be removed as
necessary, but at least annually from the wet vault, forebay/pretreatment area,
emergency spillway, weirs, and trash grates. The frequency of sediment removal
depends on the years of sediment accumulation that were incorporated into the
design volume of the wet vault’s permanent pool and forebay and on the occurrence
of any high-loading events.
- Sediment removal and disposal from underground wet vaults may currently be
regulated by the MPCA. Sediment testing, disposal, and permitting may be
required and shall be investigated on an individual site basis. Sediments must be
tested for toxicants in compliance with current disposal requirements as required
by local, state, or federal laws or regulations.
- Vault maintenance procedures must meet OSHA confined space entry
requirements, which include clearly marking entrances to confined space areas.
- Adequate access for appropriate equipment must be provided for inspection,
maintenance, and landscaping upkeep.
- It is recommended that the maintenance agreement between the city and applicant
be filed against the property with the county.
- Additional general maintenance activities and schedules are in the
Minnesota Stormwater Manual and the Minnesota BMP Manual.
7.0 Requirements for Construction Erosion and
Sediment Control Plans
- For construction projects that involve more than 200 cubic yards of cut or fill, or disturb more
than 10,000 square feet, an Erosion and Sediment Control Plan shall be prepared that meets
the standards given in the NPDES Permit for Construction Activity (MPCA) and Protecting
Water Quality in Urban Areas (MPCA, 1989).
- Erosion and sediment control plans submitted for BCWMC review shall show the proposed
methods of retaining waterborne sediments onsite during the period of construction, and shall
specify methods and schedules to determine how the site will be restored, covered, or
revegetated after construction.
- In addition, the project proposer shall:
- Provide specific measures to control erosion based on the grade and length of the slopes
on the site, as follows:
(1)
Silt fences or other erosion control features shall be placed along the toe of the
slopes that have a grade of less than 3 percent and are less than 400 feet long from
top to toe. The silt fences shall be supported by sturdy metal or wooden posts at
intervals of 4 feet or less.
(2)
Flow lengths up-slope from each silt fence shall not exceed 400 feet for slopes that
have a grade of less than 3 percent.
(3)
Silt fences or other erosion control features shall be placed along the toe of the
slopes that have a grade of 3 to 10 percent and are less than 200 feet long from top
to toe. These fences shall be supported by sturdy metal or wooden posts at intervals
of 4 feet or less.
(4)
Flow lengths up-slope from each silt fence shall not exceed 200 feet for slopes that
have a grade of 3 to 10 percent.
(5)
Diversion channels or dikes and pipes shall be provided to intercept all drainage at
the top of slopes that have a grade of more than 10 percent and are less than
100 feet long from top to toe. Silt fence shall be placed along the toe of said slopes,
and shall be supported by sturdy metal or wooden posts at intervals of 4 feet or less.
(6)
Diversion channels or dikes and pipes shall be provided to intercept all drainage at
the top of slopes that have grades of more than 10 percent. Also, diversion channels
or diked terraces and pipes shall be provided across said slopes if needed to ensure
that the maximum flow length does not exceed 100 feet. Silt fence shall be placed
along the toe of said slopes, and shall be supported by sturdy metal or wooden posts
at intervals of 4 feet or less.
(7)
Other erosion control practices such as erosion logs, compost blankets, and compost
filter berms, and other practices should also be considered for construction site
erosion control.
-
Require that silt fences, silt socks, or approved inlet protection devices be installed
around each catch basin inlet on the site and that this barrier remain in place until
pavement surfaces have been installed and/or final turf establishment has been achieved.
-
Ensure that flows from diversion channels or pipes are routed to sedimentation basins or
appropriate energy dissipaters in order to prevent transport of sediment to outflow
conveyors and to prevent erosion and sedimentation when runoff flows into the
conveyors.
-
Provide that site-access roads be graded or otherwise protected with silt fences, diversion
channels, or dikes and pipes to prevent sediment from leaving the site via the access
roads. Vehicle tracking of sediment from the construction site (or onto streets within the
site) must be minimized by installing rock construction entrances (with a minimum height
of 2 feet above the adjacent roadway and with maximum side slopes of 4:1), rumble strips
(mud mats), wood chips, wash racks, or equivalent systems at each site access.
-
-
Require that soils tracked from the site by motor vehicles be cleaned daily (or more
frequently, as necessary) from paved roadway surfaces throughout the duration of
construction.
-
Assure that silt fences and diversion channels or dikes and pipes be deployed and
maintained for the duration of site construction. If construction operations interfere with
these control measures, the silt fences, diversion channels or dikes and pipes may be
removed or altered as needed but shall be restored to serve their intended function at the
end of each day.
-
Specify that all exposed soil areas must be stabilized as soon as possible, but in no case
later than 14 days after the construction activity has temporarily or permanently ceased. A
schedule of significant grading work will be required as part of the erosion and
sedimentation control plan.
-
Require that temporary or permanent mulch be uniformly applied by mechanical or
hydraulic means and stabilized by disc-anchoring or use of hydraulic soil stabilizers.
-
Provide a temporary vegetative cover consisting of a suitable, fast-growing, dense
grass seed mix spread at 1.5 times the usual rate per acre. If temporary cover is to remain
in place beyond the present growing season, two-thirds of the seed mix
shall be composed of perennial grasses.
-
Provide a 4-foot wide sod buffer along the curb line of all streets adjacent to the site and
along all property boundaries where runoff could leave the site.
-
Specify a permanent vegetation cover consisting of sod, a suitable grass-seed mixture, or
a combination thereof. Seeded areas shall be either mulched or covered by fibrous
blankets to protect seeds and limit erosion.
-
Provide temporary on-site sedimentation basins when 10 or more acres of disturbed area
drain to a common location. Install temporary sediment basins where appropriate in areas
with steep slopes or highly erodible soils drain to one area. On-site detention basins shall
be designed to achieve pollutant removal efficiencies equal to or greater than those
obtained by implementing the criteria set forth by the NPDES Permit for Construction
Activity (MPCA, 2008) and Protecting Water Quality in Urban Areas (MPCA, 1989).
8.0 Streambank Erosion and Degradation Control Streambank erosion and streambed degradation control measures must:
-
Be employed whenever the net sediment transport for a reach of stream is greater than zero or
whenever the stream’s natural tendency to form meanders directly threatens damage to
structures, utilities, or natural amenities in public areas.
-
Include effective energy dissipation devices or stilling basins to prevent streambank or
channel erosion at all stormwater outfalls. Specifically:
-
Outfalls with outlet velocities of less than 4 fps that project flows downstream into the
channel in a direction of 30° or less from the normal flow direction generally shall not
require energy dissipators or stilling basins, but they may need some riprap protection.
-
Energy dissipators shall be sized to provide an average outlet velocity of no more than
6 fps. If riprap is also used, the average outlet velocity may be increased to 8 fps.
-
Riprap stilling basins shall not be used where outlet velocities exceed 8 fps.
-
Specify riprap consisting of natural angular stone suitably graded by weight for the
anticipated velocities.
-
Provide riprap to an adequate depth below the channel grade and to a height above the outfall
or channel bottom so as to ensure that the riprap will not be undermined by scour or rendered
ineffective by displacement.
-
Specify that riprap be placed over a suitably graded filter material or filter fabric to ensure
that soil particles do not migrate through the riprap and reduce its stability.
Streambank stabilization and streambed degradation control structures must be submitted to the
BCWMC for review. The review will consider the need for the work, the adequacy of design, unique
or special site conditions, energy dissipation, the potential for adverse effects, contributing factors,
preservation of natural processes, and aesthetics.
9.0 Regulatory Agencies
9.1 Minnesota Department of Natural Resources (DNR)
Any project constructed below the ordinary high water mark (OHW) which alters the
course, current, or cross-section of state public waters or public waters wetlands is
subject to the regulatory jurisdiction of the DNR. This includes filling, excavation,
construction of structures, water level control, and drainage projects.
Questions concerning the DNR’s role in water resource management should be directed to the DNR
Division of Waters, Metro Region, 1200 Warner Road, St. Paul, Minnesota 55106 (651)
772-7910), http://www.dnr.state.mn.us/waters/index.html.
9.2 Minnesota Pollution Control Agency (MPCA)
An NPDES/SDS General Stormwater Permit for Construction Activity is required from the
MPCA for projects which disturb one acre or more of soil.
As part of the permitting process, the owner and operator must create a stormwater pollution
prevention plan (SWPPP) that explains how stormwater will be controlled. After a SWPPP has
been completed, site owners and their construction operators may apply for the permit by
submitting an Application for General Stormwater Permit for Construction Activity (MN
R100001) to the MPCA.
Questions concerning the construction stormwater permit program and MPCA’s role in
water resource management should be directed to the MPCA, 520 Lafayette Road, St.
Paul, MN 55155, (651) 206-6300 http://www.pca.state.mn.us/water/index.html.
Appendix A Application Form
Appendix B Water Quality Definitions
Appendix C General Review Requirements
|