Crane Lake Improvement Project

Minnetonka

Project Number: CL-3

Project Status   |  Complete

At their meeting on March 21, 2019, the BCWMC approved the project's feasibility study and chose to implement Option 3 from the study. At their meeting on May 16, 2019, the BCWMC approved the 90% design plans for the project. Construction is expected in early 2020.

After no comments were received during a public hearing on September 19, 2019, the BCWMC officially ordered this project by resolution (see "more information"). The BCWMC also approved an agreement with the City of Minnetonka for the design, construction, and ongoing maintenance of the project.

The project was constructed by the city in 2019 and 2020. A final report was approved December 2020.


Project Funding   |   Not Grant Funded

The total cost of this project was $650,440.38. The City of Minnetonka will paid $270,440.38. The BCWMC will paid the remaining $380,000 from a tax levy on watershed residents.


Project Description

This project was constructed in conjunction with the reconstruction of Ridgedale Drive in the City of Minnetonka and treats runoff from 13.3 acres of developed land that previously flowed untreated into Crane Lake. The project removes an estimated 9 pounds of total phosphorus and 3,500 pounds of total suspended solids from the runoff each year.

The project includes construction of a 12,250 cubic-foot underground stormwater storage and pretreatment system, a wet well with a 30 gallon-per-minute (0.7 cubic-feet-per-second) pump, and a series of infiltration basins. A granular filter media and underdrains were installed as a backup system to allow for filtration. These components were constructed in a new park just east of Ridgedale Drive and will include educational signage about the treatment system and Crane Lake in the future.

More Information

Final Project Report (Dec 17, 2020)

Resolution 19-09 Ordering Project (Sept 19, 2019)

BCWMC Engineer Memo on 90% Plans (approved May 16, 2019)

90% Design Plans

Feasibility Study (Option 3 approved March 21, 2019)

Presentation of Feasibility Study (March 21, 2019)